The Flat Run Solar project is located in Taylor County, Kentucky. The 55 MW project will sit on 450 acres of land and, in addition to providing clean, renewable energy, the project will have a positive economic impact in the local area, namely through local construction jobs and purchases of local goods and services.

ENGIE is committed to being the best local business and neighbor that we can be in the county. Construction will begin Q1 2023 and will become operational by Q4 2024.

Solar Array

Overview

  • Location: Taylor County, Kentucky
  • Status: Permitting
  • Expected COD: 12/31/2024
  • Project MW:  55 MWac
  • Real Estate: Long-term lease and purchase agreements in place with local landowners
  • Interconnection: East Kentucky Power Cooperative

ENVIRONMENT

  • NEPA review completed
  • Aquatic resources delineation report completed with Approved Jurisdictional Determination by the US Army Corps of Engineers
  • Mussel Survey completed
  • Phase 1 Environmental Site Assessment completed
  • Environmental lien and AUL search completed
  • Federal Aviation Administration screening completed
  • Noise and traffic study completed
  • Preliminary geotechnical survey completed
Working in the field with solar
Solar

PERMITTING

State Permit obtained and Certificate to Construct granted by the Kentucky State Board of Electric Generation and Transmission Siting on October 7th, 2021