Sand Fork Solar™ project in Texas
Overview
In June 2019, ENGIE entered into a Power Purchase Agreement (PPA) with Target Corporation for 89 MW of capacity from the Sand Fork Solar™ Project. This Texas solar project came online in Q1 2021. In addition to providing clean, renewable energy, the project will have a positive economic impact in the local area, namely through local construction jobs and purchases of local goods and services.
- Location: Jones County, Texas
- Status: Operational
- Project MW: 200 MW
- Transmission: ERCOT
- Project Area: 2,200+ acres
- Customer: Target
Project Details
REAL ESTATE
- Over 2,200 acres of land under long-term lease, including all planned solar panels, collection lines, and access roads
INTERCONNECTION
- Generator Interconnection Agreement executed in June 2019
- 345 kV Interconnection at Lone Star Transmission’s Phantom Hill Switching Station